Skip to main content

Information for cargo ships

This page provides you with information on crane operator training. It is the area of use of the crane that determines the training that applies to the different types of cranes.

Regulations for the training of crane operators on Norwegian ships

Training of crane operators on Norwegian ships is regulated in the Regulations of 17 January 1978 No. 4 on loading and unloading facilities on ships (FOR-1978-01-17-4).
Training in Enclosed Waters
For cranes used for loading or unloading in completely enclosed waters, as well as internally on board the vessel, no formal training or certification of crane operators is required, only that the person must be at least 18 years of age, cf. section 24(2).

The training shall then be safeguarded by the following regulations:

•    ISM Code Chapter 6 (on the vessels where it applies)
•    Section 22 of the Ship Safety and Security Act, 
•    ASH Regulations § 2-6.

Responsibilities and requirements for the shipping company

The company is responsible for ensuring adequate training of affected personnel in accordance with the regulations mentioned above. The training must be documented in writing. The company has a great responsibility to ensure that the use of these cranes is safe. 

Training in open waters

For cranes used for loading and unloading in open waters, the Regulations on cranes used for loading and unloading on ships in open waters (FOR-1986-01-13-31) apply. Crane operators must have undergone recognised practical and theoretical training regarding cranes and lifting equipment.

Lifting ears/"pad eyes"

Requirements for dimensioning and testing of lifting ears/"pad eyes" are regulated in accordance with RSV 13-2020.

Lifting personnel with a crane

There are no technical requirements in the NMA's regulations in connection with personnel lifting and temporary work at height. 
Risk assessment and documentation of measures are nevertheless important in accordance with the ASH prescript.

  1. Hazards on board must be uncovered. Once the danger has been identified, an assessment must be made of the risk posed by the danger. Such a risk assessment shall be carried out on a regular basis and by: 
    a) the introduction of new work equipment or new technology, and 
    b) other changes in the organisation or planning of work that may have an impact on the safety and health of employees.
  2. The results of the risk assessment must be documented in writing.
  3. If a risk to the safety and health of workers is identified, the necessary measures must be taken to remove or reduce the hazards.
    Furthermore, we refer to  Appendix 1 of Regulation No. 8: "Provisions on the use of work equipment for temporary work at heights."

The NMA has previously assessed this type of work operation in relation to Regulation No. 8, and in this context has prepared the following guidelines:

  1. Work baskets must be dimensioned for their intended use
  2. Fastening/connecting between work basket and crane shall be in accordance with manufacturer(s) recommendations
  3. The crane used for the operation must comply with standard EN 13852-1:2004, Chapter 5.8
  4. Operational limitations apply in accordance with standard EN 13852-1:2004, chapter 7.2.5

It is assumed that the competent person assures that the above points have been taken care of and that this is documented. The NMA expects the crane to be certified for personnel lifting (man riding) by a qualified person.

A-frame with matching winch

The Regulations on cranes used for loading and unloading on ships in open waters (FOR no. 31) deal with lifting in open waters beyond the ship's side, as an A-frame does. This premise therefore applies to A-frame. 
If the release arrangement is used in relation to the ROV, the IMCA standard for ROV release arrangements can be used as an equivalence to the Regulations.

Possibility of using the class regulations

Crane standards such as DNVGL-ST-0377 and DNVGL-ST-0378 may be considered equivalent to the Norwegian Regulations FOR No. 4 and FOR No. 31, provided that the company applies in writing and that the class regulations are met.
Part of the reason for this is that mobile offshore units already have this acceptance, and that the NMA acknowledges that our regulations are somewhat outdated and do not coincide with other standards such as EN 13852-1.

The NMA may accept that class standards are used as an equivalent to our Regulations, provided that the shipowner applies in writing and the class standard is met in full.

Excavator/self-unloader:

An excavator is to be regarded as a loading and unloading device in accordance with FOR no. 4, where the current practice is as follows:

  • Excavator with complete overhead crane, crane track, crane rail and support plates as well as end plates for the crane runway, - everything that is above deck must be checked, tested and certified by a qualified person type A as described in our Regulations of 17.01.1978 no. 4 on loading and unloading facilities on ships.
  • In the event of a modification of the lifting device, the aids will have to be updated. It will then be expected from the NMA that the cargo chart will be updated to correspond with e.g. an extended arm.

Forklift:

Forklifts must meet the requirements set out in FOR no. 507 § 18.